Update November 2013


Work on the western oval of Barnard Park is now well under way.

Reticulation is near completion and the construction of the fire track has commenced.

064.jpg


Earth works and raised mounds have been completed along with soil preparation.

063.jpg

A water bore has been sunk and a bore shed erected which is currently awaiting a fit out.

059.jpg

It is anticipated that grass laying will commence shortly and the western oval completed by 30 November.

Work on the eastern oval is scheduled to commence January 2014 and be completed by the end of June.

At the 9 October 2013 Council meeting a revised Busselton Foreshore Master Plan was adopted as part of a public consultation process along with the proposed Development Guide Plan for the Busselton Foreshore.  This revised plan was advertised for the period October 23 - November 19 2013.